Kunshan 5,000 m² SAC Semiconductor Cleanroom

Completed in Kunshan in 2020, this 5,000 m² SAC semiconductor cleanroom targets ISO 7 across a large production area.

Explore this application
Completed in Kunshan, China, in 2020, this project covered approximately 5,000 m² of ISO 7 clean space for semiconductor operations. The brief required particle control, coordination with production equipment, and maintainable access across a large footprint. SAC modular cleanroom construction allowed the enclosure to be assembled at the site around those requirements. The scope combined walls and cleanroom ceiling systems with HVAC and filtration, lighting, electrical services, automation, and monitoring. On-site assembly, commissioning, and validation were also included. The recorded delivery period was eight months, reflecting the scale stated in the project record rather than a general lead-time promise. This semiconductor clean room case illustrates the use of a site-assembled approach for a substantial industrial facility. The public description protects the client's identity and does not publish equipment layouts, process technology, or measured operating data.
Kunshan 5,000 m² SAC Semiconductor Cleanroom
5,000 m² Controlled area
8 months Delivery
ISO 7 Cleanroom class
01
THE CHALLENGE

Working Around Real Project Constraints

Create approximately 5,000 m² of ISO 7 semiconductor clean space with particle control, equipment coordination and maintainable access.

02
THE SOLUTION

Engineered for the Process

A large site-assembled SAC modular cleanroom provided approximately 5,000 m² of ISO 7 space for semiconductor operations in Kunshan.

SCOPE OF DELIVERY

A Coordinated Cleanroom Package

The project package was coordinated as a complete system, keeping architectural, mechanical and controls interfaces aligned from design through qualification.

  • 01Site-assembled modular walls and ceiling for a 5,000 m² semiconductor cleanroom
  • 02HVAC and filtration serving the ISO 7 clean space
  • 03Lighting, electrical, automation and monitoring systems
  • 04On-site assembly, commissioning and validation
APPLICATION & SELECTION

Scoping a Semiconductor Cleanroom Package

For a new semiconductor facility, describe the actual production or support operation before choosing the room configuration. Use the process brief to separate room requirements from individual tool requirements.

Planning guidance for similar projects. The project snapshot and delivery scope above describe this case; the considerations below help define a new project brief.

Identify process-specific contamination risks

Where airborne chemicals could affect the product or process, define the substances and assessment approach separately. Chemical air cleanliness has its own assessment framework rather than being inferred from an airborne particle class.

Assess airflow with operating cost in view

Berkeley Lab research highlights the energy implications of cleanroom air systems and the risk of excessive airflow design. Evaluate the airflow basis against contamination-control needs rather than treating additional air volume as an automatic improvement.

Plan electrostatic control for the operation

Semiconductor fabrication and electronics assembly have different ESD and electrostatic-attraction challenges. Ask the process owner to identify sensitive tools, materials and handling steps before specifying the appropriate control programme.

DEFINE YOUR REQUIREMENTS

What to share for a similar project

Use these inputs to discuss the layout, interfaces and delivery scope with our team.

Explore site-assembled (SAC) solutions
  • Production process and cleanliness requirements by zone
  • Equipment layout, heat loads and service connections
  • Ceiling access, service routes and maintenance clearances
  • Existing building constraints and construction phases
  • Acceptance criteria and intended operating conditions
PROJECT QUESTIONS

Planning a large semiconductor cleanroom

Is ISO 7 suitable for every semiconductor process?

Suitability depends on the operation. Airborne particle classification describes one environmental attribute; process-specific chemical contamination and electrostatic requirements need their own assessment.

What information is needed to size a large cleanroom package?

Send the tool list, room layout, equipment heat loads, utilities, exhaust requirements, personnel numbers and planned production phases. Include any tool-vendor environmental tolerances and future expansion areas.

How should phased commissioning be discussed?

Mark the proposed handover zones and the equipment-installation sequence. Request an agreed test schedule and record which occupancy state will apply to each acceptance test.